EDF Renewables unveils phase 2 of Blyth Offshore project
EDF Renewables plans to build phase two of the Blyth Offshore Demonstrator (BOD) wind farm off the coast of Northumberland using floating offshore wind technology.
The capacity for phase two has still to be finalised but the current consent for BOD wind farm is for a maximum of 99.9MW, leaving a remaining capacity of 58.4MW.
The first phase of the wind farm, consisting of five wind turbines, was built in 2017. It has a generating capacity of 41.5MW and the first UK offshore wind farm to utilise float and submerge gravity base foundations, as well as 66KV rated inter array and export cables to connect the turbines to an onshore substation.
EDF Renewables is already working on project planning for phase two with a consent variation and procurement activities underway to use the Blyth site for the installation of up to five more turbines, in an already identified location 14kms offshore in depths of around 55 metres. On completion, it would be among the first projects of this kind in English waters.
The turbines to be installed in the BOD Phase two project will be constructed on floating sub structures. The project has yet to select the key contractors including the turbine supplier but a range of floating technology options are being considered, with the final design still to be determined by further detailed engineering studies.
A key requirement of the project is to demonstrate new and innovative technologies that have potential to reduce the cost of offshore wind (floating and fixed) developments in the future. As a result, EDF Renewables is working closely with suppliers and research organisations including the Offshore Renewable Energy Catapult to ensure these technologies and approaches are fully explored and incorporated where appropriate.
Director of Offshore wind at EDF Renewables, Michele Schiavone said: "We are very excited about this next phase of the BOD project and want to further the demonstration of construction and operation of floating turbines to show that floating wind is technically feasible and cost competitive in water depths of 50-60 metres.
"With the Contract for Difference (CfD) mechanism providing a potential route to market, we are confident that floating turbine technology can accelerate the UK’s journey to a net zero future where clean energy powers all our lives. We will use the project to support the further development of this emerging technology.
“We are ambitious when it comes to offshore wind and already have two operational offshore wind sites at Blyth and Teesside. We are currently working on our 450 MW Neart na Gaoithe project in the Firth of Forth in Scotland (a joint venture with ESB) and our Irish Codling project (a joint venture with Fred.Olsen Renewables) which will have a capacity of up to 1.5GW."
The development timescale for BOD phase two has not yet been finalised. However, subject to detailed programming, the target is for it to be fully commissioned by Spring 2025.
In a recent video update on the Hinkley Point C nuclear plant, EDF Managing Director Stuart Crooks said 18 of its 20 milestones had been reached last year but estimates three months were lost owing to the pandemic "and we could lose up to three more months in 2021". The first 3.5km tunnel for the cooling water was completed just before Christmas (click here).
- Ørsted Q&A: How Does Renewable Energy Impact Biodiversity?Renewable Energy
- How a Coal Terminal Will Drive Renewable Energy in the UKRenewable Energy
- Shell, Equinor, Uniper & the Global Energy Storage ProblemRenewable Energy
- How Schneider Electric will Smash 2024 Sustainability GoalsSustainability