Nov 8, 2013

UK's offshore wind demonstration site a go

Admin
3 min
The development of the UK’s largest offshore wind demonstration site – regarded as a pivotal strand in helping to lower the costs assoc...

The development of the UK’s largest offshore wind demonstration site – regarded as a pivotal strand in helping to lower the costs associated with Round 3 offshore wind farms – has received a boost with dual planning consents being given to the construction of the site and the onshore substation.

The Marine Management Organization (MMO) has granted permission to The National Renewable Energy Centre (Narec) to construct the grid-connected 99.9MW demonstration project, comprising 15 turbines in three arrays in depths of 35m, 45m and 55m off the coast of Blyth in Northumberland including cables back to shore.

Northumberland County Council has also granted permission for the construction of the supporting onshore infrastructure including the electrical substation that will transfer the power created by the demonstration turbines to the grid.

The project is the first large-scale deep water demonstration site in the UK to be granted both offshore permits and onshore consent, and is seen as an essential facility for industry to be able to test next-generation offshore wind technology cost-effectively in realistic environmental conditions before commercial production.

For Narec, the £350 million demonstration site will be the final piece in the jigsaw as part of its strategy to provide a complete suite of independent open access test facilities, enabling manufacturers to reduce the risks and costs associated with developing the new technologies that will be needed in Round 3 projects.

“We’re delighted to have reached such an important milestone and my thanks go to the project team including consultants Natural Power and Turner & Townsend in getting us to this stage,” said Andrew Mill, Narec’s chief executive. “We’re now in talks with potential investment partners to build out the demonstration site. Construction of the first array is targeted to be completed in 2015.”

Shaun Nicholson, head of Offshore Marine Licensing for the MMO, said: “The Blyth project is the largest site we have approved for the testing of turbine devices.

“We aim to enable sustainable growth in making decisions about developments at sea. We consider economic benefits alongside any adverse impacts, such as on the environment and other users of the marine area. We have worked with Narec to ensure the development satisfied such conditions.”

*The Blyth Offshore Wind Demonstration Site is consented for up to 15 turbines positioned in three arrays in depths of 35m, 45m and 55m. The site is one of four that were granted a lease by The Crown Estate in 2010. Since then, Narec has been working with the Marine Management Organization to meet the rigorous approval criteria.

The site will be used by manufacturers and wind farm developers to learn new approaches across the supply chain including the study of alternative foundation types and construction methods for the development, deployment, operation and maintenance of new turbine technologies.

Narec has invested over £150 million of UK Government, private sector and European Union funding to create a unique integrated portfolio of research, testing and demonstration facilities for the offshore renewables industry, operated on an open-access, commercial basis in Blyth, Northumberland, England.

 

Share article

Apr 23, 2021

Drax advances biomass strategy with Pinnacle acquisition

Drax
Biomass
Sustainability
BECCS
Dominic Ellis
2 min
Drax is advancing biomass following Pinnacle acquisition it reported in a trading update

Drax' recently completed acquisition of Pinnacle more than doubles its sustainable biomass production capacity and significantly reduces its cost of production, it reported in a trading update.

The Group’s enlarged supply chain will have access to 4.9 million tonnes of operational capacity from 2022. Of this total, 2.9 million tonnes are available for Drax’s self-supply requirements in 2022, which will rise to 3.4 million tonnes in 2027.

The £424 million acquisition of the Canadian biomass pellet producer supports Drax' ambition to be carbon negative by 2030, using bioenergy with carbon capture and storage (BECCS) and will make a "significant contribution" in the UK cutting emissions by 78% by 2035 (click here).

Drax CEO Will Gardiner said its Q1 performance had been "robust", supported by the sale of Drax Generation Enterprise, which holds four CCGT power stations, to VPI Generation.

This summer Drax will undertake maintenance on its CfD(2) biomass unit, including a high-pressure turbine upgrade to reduce maintenance costs and improve thermal efficiency, contributing to lower generation costs for Drax Power Station.

In March, Drax secured Capacity Market agreements for its hydro and pumped storage assets worth around £10 million for delivery October 2024-September 2025.

The limitations on BECCS are not technology but supply, with every gigatonne of CO2 stored per year requiring approximately 30-40 million hectares of BECCS feedstock, according to the Global CCS Institute. Nonetheless, BECCS should be seen as an essential complement to the required, wide-scale deployment of CCS to meet climate change targets, it concludes.

Share article