Chevron and GE Vernova: Tackling AI's Energy Challenges

Share this article
Share this article
Prioritise Us on Google
Some AI facilities now require upwards of 200 megawatts, equivalent to the consumption of a small city
Chevron and GE Vernova plan 4GW of gas power plants for data centres, targeting AI's massive electricity needs with first facilities launching in 2027

Across the United States, data centres are bracing for an ongoing spike in electricity demand.

This surge primarily stems from technologies such as Artificial Intelligence (AI) which place significant stress on power grids.

A firm prediction by Gartner suggests that by 2027, 40% of AI facilities will be operationally limited due to electricity shortages.

Specifically, workloads from generative AI are expected to boost data centre power consumption by a staggering 160% within the next two years.

The current grid infrastructure is often found lacking when matched with these heavy demands.

Some AI-focused facilities now need more than 200MW, an amount that equates to the power needs of a small city.

As a result, several regions — such as Dublin, Singapore and certain parts of Virginia — are witnessing a restriction in constructing new data centres due to power availability concerns.

Key facts
  • 4 gigawatts: Total planned power generation capacity
  • 7: Number of GE Vernova 7HA gas turbines secured for initial projects
  • 90%: Potential carbon dioxide capture rate from planned carbon capture technology

In response, following the announcement by President Trump concerning significant investments in data centres, energy giants like GE Vernova, Chevron and investment firm Engine No. 1 have shared plans to build power generation facilities.

These units will be directly attached to data centres all over the US.

GE Vernova's strategic role

A crucial agreement has been sealed for the acquisition of seven GE Vernova 7HA gas turbines, laying the groundwork for what's termed as "power foundries."
These installations, fueled by natural gas, are set to generate electricity for adjacently located data centres, skirting traditional transmission routes.

Youtube Placeholder

Planned across the Southeast, Midwest and West US regions, this strategy aims at minimising load on the existing power distribution frameworks.

Forward-thinking technical innovations

The arrangement has charted out a total generation capacity of 4GW, sufficient to cater to about 3 to 3.5 million American homes.

The technical plan also includes measures for future incorporation of carbon capture and storage technologies, potentially slashing more than 90% of carbon dioxide emissions from the operation.

There's also capacity for integrating renewable energy resources, though the specifics have not been disclosed.

Chris James, Founder and Chief Investment Officer of Engine No. 1

Chris James, Founder and Chief Investment Officer of Engine No. 1, says: “Energy is the key to America’s AI dominance.

"By using abundant domestic natural gas to generate electricity directly connected to data centres, we can secure AI leadership, drive productivity gains across our economy and restore America’s standing as an industrial superpower.”

Broader industry impact and development

The strategic shift in data centre power supply from grid connectivity to onsite generation illustrates a significant evolution in data centre infrastructure strategy.

The reliance on direct connections avoids the limitations presented by regional power capacities, which is particularly relevant given the burgeoning data processing, cloud computing and AI operations escalating power needs.

The partnership’s ‘power foundries’ will generate electricity from natural gas

Operation is set to begin by the end of 2027, with room for further expansion beyond 4GW.

The layout also contemplates future grid connections, which could allow selling excess power to the wider electricity markets.Mike Wirth, Chief Executive Officer and Chairman of Chevron Corporation, says: “We are proud to play our part in bringing to fruition President Trump's vision for a new American golden age, powered by our enormous energy resources and unrivalled workforce.”

Mike Wirth, Chief Executive Officer and Chairman of Chevron Corporation

GE Vernova's involvement brings expertise from its power, wind and electrification segments to ensure the project's success.

Scott Strazik, Chief Executive Officer for GE Vernova, says: “We are excited to enable the advancement of data centre growth in the US by supporting delivery of critical power needs to customers using innovative solutions.

Scott Strazik, Chief Executive Officer for GE Vernova

"GE Vernova is uniquely positioned to provide the energy systems and support required to make this large-scale endeavour possible, as the leading US energy manufacturer.”

The new power model combining generation with consumption onsite proposes a robust response to new demands faced by the data centre industry.

It represents not just an adaptation to energy challenges but a proactive measure that could define future standards in data centre power infrastructure.


Explore the latest edition of Energy Digital Magazine and be part of the conversation at our global conference series, Sustainability LIVE.

Discover all our upcoming events and secure your tickets today.


Energy Digital is a BizClik brand

Company portals