Gas Pipeline Project through 'Bread Basket' of France

By Admin
GRTgaz is currently extending Frances gas transmission network with the Haute de France II (HDF II) pipeline project. Max Streicher GmbH & Co.KG a...

GRTgaz is currently extending France’s gas transmission network with the Haute de France II (HDF II) pipeline project. Max Streicher GmbH & Co. KG a.A, of Germany, has been commissioned by GRTgaz to complete the second construction lot.

Streicher is laying 51.7 kilometres of gas pipeline between Corbie and Cuvilly in the Picardy region near Amiens. Working in the “bread basket” of France presents new challenges to pipeline construction experts and calls for new laying techniques.

The Haute de France II as a parallel pipeline to the existing Haute de France I. HDF II starts in French Dunkirk, near the Belgian border, and runs south. The soil in the generally flat area for the pipeline is loose and stony.

A total length of 370 meters is being laid using micro-tunneling drilling techniques. Countless streets and existing lines have to be crossed using closed methods of laying pipeline. The Luce and Avre rivers will be crossed using open laying techniques.

In the area around the Somme River a new trenchless construction method is to be used. The 1,120 meter stretch will be crossed using the direct pipe method. Direct pipe is a combination of two established laying techniques, horizontal directional drilling (HDD) and micro-tunneling.

Pipeline construction and agriculture

The unique ecological requirements for completing this work affect the whole construction process. The area that Haute de France II runs through is known as the bread basket of France. The focus of the process is to protect arable land and ensure sustainable soil quality.

Therefore in bad weather and at a certain level of soil moisture construction work is halted so that the soil is not negatively affected. To ensure that the work is as efficient as possible, whenever possible the construction methods are decided on in agreement with the Chamber of Agriculture.

Double welding power

Work on the Haute de France II project is carried out using the CRC-EVANS welding method. This involves welding the root of the seam from the inside with four torches simultaneously.

Automatic welding machines with double burner systems are used for the filler layers as they allow welding from two places at a distance of 10 centimeters simultaneously. This allows for higher deposition rates than with other methods. The production rate is also significantly higher. The current top performance rate in Streicher’s work is more than 40 welding seams per day.

In total at the second construction site, approximately 3,200 seams will be welded and three valve stations and one receiving station will be completed. Since March nearly 230 Streicher employees have been working north of Paris on site on the project. The firstpressure tests should take place in October and the gas pipeline is due to be ready for use in March 2014.

Share
Share

Featured Articles

How Siemens Gamesa Became a Global Wind Power Leader

One of the world’s largest wind companies, Siemens Gamesa played a major role in the early years of electricity and is now a leader in the renewable space

Earth Day 2024: Renewable Energy Key To Sustainable Future

Celebrated annually on 22 April, Earth Day 2024’s main theme centres around ‘People vs Plastics’ but also looks at sustainability as a whole

What's Apple’s Promise on Clean Energy and Water Investment?

Tech giant Apple is working to increase its sustainable output, supporting more than 18GW of clean energy use & billions of gallons in water savings

Data Centre Demand Putting Pressure on Energy Capabilities

Technology & AI

Q&A with Hitachi Energy’s EVP & Head of North America

Sustainability

OMV Takes Strides in Energy Efficiency & Emissions Reduction

Sustainability